1.
Using an example, describe the generic project life cycle model. Also, list and
describe the numerous issues that pertain to each stage of the project life
cycle.
2.
Describe the different analysis techniques used in project selection. In your
opinion which one is the most common technique? Why?
3.
A project is composed of 7 activities whose time estimates are listed in the
table below:
Activity
|
Estimated duration (in weeks)
|
||
Optimistic
|
Most likely
|
Pessimistic
|
|
1-2
|
1
|
3
|
7
|
1-3
|
1
|
4
|
7
|
1-4
|
2
|
4
|
8
|
2-5
|
1
|
1
|
1
|
3-5
|
2
|
5
|
12
|
4-6
|
2
|
5
|
8
|
5-6
|
1
|
6
|
15
|
a)
What is the probability of finishing this project before 14 weeks?
b)
What date results in a 99% probability of completion?